| § 54.01-1 | Incorporation by reference. |
| § 54.01-2 | Adoption of Division 1 of Section VIII of the ASME BPVC. |
| § 54.01-5 | Scope (modifies U-1 and U-2). |
| § 54.01-10 | Steam-generating pressure vessels (modifies U-1(g)). |
| § 54.01-15 | Exemptions from shop inspection and plan approval (modifies U-1(c)(2)). |
| § 54.01-17 | Pressure vessel for human occupancy (PVHO). |
| § 54.01-18 | Plan approval. |
| § 54.01-25 | Miscellaneous pressure components (modifies UG-11). |
| § 54.01-30 | Loadings (modifies UG-22). |
| § 54.01-35 | Corrosion (modifies UG-25). |
| § 54.01-40 | External pressure (modifies UG-28). |
| § 54.03-1 | Scope. |
| § 54.03-5 | General. |
| § 54.05-1 | Scope (replaces UG-84). |
| § 54.05-3 | Tests required. |
| § 54.05-5 | Toughness test specimens. |
| § 54.05-6 | Toughness test temperatures. |
| § 54.05-10 | Certification of material toughness tests. |
| § 54.05-15 | Weldment toughness tests—procedure qualifications. |
| § 54.05-16 | Production toughness testing. |
| § 54.05-17 | Weld toughness test acceptance criteria. |
| § 54.05-20 | Impact test properties for service of 0 °F and below. |
| § 54.05-25 | [Reserved] |
| § 54.05-30 | Allowable stress values at low temperatures. |
| § 54.10-1 | Scope (modifies UG-90 through UG-103 and UG-115 through UG-120). |
| § 54.10-3 | Marine inspectors and Coast Guard Symbol stamping (replaces UG-90 and UG-91, and modifies UG-92 through UG-103). |
| § 54.10-5 | Maximum allowable working pressure (reproduces UG-98). |
| § 54.10-10 | Standard hydrostatic test (modifies UG-99). |
| § 54.10-15 | Pneumatic test (modifies UG-100). |
| § 54.10-20 | Marking and stamping. |
| § 54.10-25 | Manufacturers' data report forms (modifies UG-120). |
| § 54.15-1 | General (modifies UG-125 through UG-137). |
| § 54.15-3 | Definitions (modifies appendix 3). |
| § 54.15-5 | Protective devices (modifies UG-125). |
| § 54.15-10 | Safety and relief valves (modifies UG-126). |
| § 54.15-13 | Rupture disks (modifies UG-127). |
| § 54.15-15 | Relief devices for unfired steam boilers, evaporators, and heat exchangers (modifies UG-126). |
| § 54.15-25 | Minimum relief capacities for cargo tanks containing compressed or liquefied gas. |
| § 54.20-1 | Scope (modifies UW-1 through UW-65). |
| § 54.20-2 | Fabrication for hazardous materials (replaces UW-2(a)). |
| § 54.20-3 | Design (modifies UW-9, UW-11(a), UW-13, and UW-16). |
| § 54.20-5 | Welding qualification tests and production testing (modifies UW-26, UW-28, UW-29, UW-47, and UW-48). |
| § 54.23-1 | Scope (modifies UB-1). |
| § 54.25-1 | Scope. |
| § 54.25-3 | Steel plates (modifies UCS-6). |
| § 54.25-5 | Corrosion allowance. |
| § 54.25-7 | Requirement for postweld heat treatment (modifies UCS-56). |
| § 54.25-8 | Radiography (modifies UW-11(a), UCS-57, UNF-57, UHA-33, and UHT-57). |
| § 54.25-10 | Low temperature operation—ferritic steels (replaces UCS-65 through UCS-67). |
| § 54.25-15 | Low temperature operation—high alloy steels (modifies UHA-23(b) and UHA-51). |