DEIF Uni‑line is a modular control system for shaft‑driven generators and PTO units, providing automatic load sharing, voltage/frequency regulation and integrated protection.
Inspector Detail
▸
Common issues
- Nuisance trip on reverse power or under/over frequency protection from incorrectly set relays after commissioning
- Loss of communication between controller and governor/AVR interface causing hunting or load-sharing instability
- Load-sharing imbalance between paralleled generators from degraded CAN bus wiring or termination
- Synchronizing failure (breaker will not close) from phase sequence or voltage-matching window errors
- Firmware/parameter mismatch after a controller replacement leading to incorrect protection curves
- Sensor/CT wiring faults producing false current or power readings
- Backup battery failure causing controller reset or loss of settings during a power dip
Inspection checklist
- Verify controller display readings against independent meters (voltage, frequency, current, power)
- Check load-sharing balance between paralleled generators under varying load
- Test protection functions (reverse power, over/under frequency, over/under voltage) against setpoints where practical
- Inspect CAN bus/communication wiring and terminating resistors
- Check backup battery condition and charging circuit
- Review event/alarm log for recurring trips or communication faults
- Confirm synchronizing (breaker close) sequence operates within the matching window
- Verify a current parameter backup exists and matches commissioning settings
Service intervals
| Parameter/settings backup verification | annually or after any firmware update |
| Protection function test (reverse power, over/under frequency) | annually or at each class survey |
| Backup battery check/replacement | per maker recommendation, typically every 3-5 years |
| CAN bus/wiring inspection | annually |
| Load-sharing calibration check | annually or after generator/governor work |
Critical spares
- Backup battery for the controller
- Spare controller module or display unit of the same type, pre-programmed where possible
- CAN bus terminating resistors and connectors
- Current transformers matched to the installed rating
- Control circuit fuses
Safety
- Live testing on generator control/protection circuits carries electric shock risk - isolate and lock out where possible
- Incorrect parameter changes can defeat reverse power or overcurrent protection, risking equipment damage or fire
- Synchronizing errors can cause severe mechanical/electrical shock to the generator and its prime mover
- Arc flash risk when working in the switchboard/controller cabinet under load
Class survey
Class surveyors typically check protection function test records, synchronizing/load-sharing performance, and confirm the as-fitted parameter set matches the approved electrical protection coordination study.
Components & Design
Component data being added…
Technical Data
🤖 Ask about this model
One free question — answered like a marine engineer. No account needed.
Suppliers & Spare Parts
Direct links to manufacturer, datasheet, spare-parts portal and dealers — request access below.
📄 Request sourcing links & documentsCases, daily reports, timesheets and AI troubleshooting in the OceanSphere Marine app — free for 14 days.
Start free trial →Find manufacturers, repair shops and spare-part dealers in the Maritime Network — our global company directory.
Maritime Network →DNV type approval
Verified against the DNV Approval Finder — the certificate below is issued by DNV, not by us.
- Certificate
- TAA00000Z2
- Approved as
- Electrical Measuring and Protection Relay · Instrumentation and Automation
- Certificate holder
- DEIF A/S (Denmark)
- Valid until
- 2028-01-20